Rolling along…

A lot has happened since we moved into our new location.  We now have most of our equipment on site and have construction underway.  We began demolition of floors and some other areas while waiting for plan approval and permits from the City which came through last week.  We have a lot of photos and more updates on Facebook – check it out!

Milestones

We’ve covered some milestones recently on our brewery project. We took possession of our new location earlier this month. We are very fortunate to have a HUGE space to grow into and a great landlord. In the last week or so we had our ABC Public Notice posted in our window to keep the licensing process moving along. Our offices have been painted and are ready for (sparse) furnishings to start out. The plans for improvements needed to make the building brewery ready were also submitted to the City of Redlands this week and we are anxious to get our building permits in hand so work can begin. For now it’s a big empty space but our new 30 barrel brewhouse is coming in early May along with other equipment.